\chapter{Actions}
In order to avoid the realization of the identified risks, we applied some of our preventive actions.
\section{Initial actions table}
\begin{table}[h!]
\begin{center}
\begin{tabular}{|p{0.5cm}|p{3cm}|p{3cm}|p{2cm}|p{1.5cm}|p{1.5cm}|p{1.5cm}|p{1cm}|}
\hline
Id & Origin & Description & Accountable & Target date & Realisation & State \\
\hline
1 & Lack of knowledge from the developer & C++ training & Thomas & 22 Jan & 23 Jan & Closed \\
\hline
2 & Team work \& version management & Git repository creation & Thomas & 05 Feb & 05 Feb & Closed \\
\hline
3 & Input needed & Taking pictures & Thierry & 22 Jan & 22 Jan & Closed \\
\hline
4 & Report to write in english & Specifications translation & Emilie & 22 Jan & 22 Jan & Closed \\
\hline
5 & Set up the dev tools & Install Linux / OpenCV & Thomas & 01 Feb & 02 Feb & Closed \\
\hline
6 & Remember stuff to do & Actions table writing & Marion & 05 Feb & 04 Feb & Closed \\
\hline
7 & Git Repository not well organized & Git cleaning & Thomas & 05 Feb & & Open \\
\hline
8 & Compatibility with the other team & Defining subskeletons format & Thierry & 06 Feb & & Open \\
\hline
9 & We love sushi & Sushi eating with the client & Thierry & 13 Feb & & Open \\
\hline
\end{tabular}
\end{center}
\caption{Initial actions table}
\end{table}
\section{Final actions table}
\begin{table}[h!]
\begin{tabular}{|p{0.5cm}|p{3cm}|p{3cm}|p{2cm}|p{1.5cm}|p{1.5cm}|p{1.5cm}|p{1cm}|}
\hline
Id & Origin & Description & Accountable & Target date & Realisation & State & Risk table\\
\hline
1 & Project management & Meeting with the industrial supervisor & Thomas & 15 Jan & 15 Jan & Closed & \\
\hline
2 & Need of specifications & Meeting with the client & Thierry & 22 Jan & 22 Jan & Closed & \\
\hline
3 & Lack of knowledge from the developer & C++ training & Thomas & 22 Jan & 23 Jan & Closed & \\
\hline
4 & Team work \& version management & Git repository creation & Thomas & 05 Feb & 05 Feb & Closed & \\
\hline
5 & Project management & Meeting with the industrial supervisor & Thierry & 21 Jan & 21 Jan & Closed & \\
\hline
6 & Input needed & Taking pictures & Thierry & 22 Jan & 22 Jan & Closed & \\
\hline
7 & Report to write in english & Specifications translation & Emilie & 22 Jan & 22 Jan & Closed & \\
\hline
8 & Set up the dev tools & Install Linux / OpenCV & Thomas & 01 Feb & 02 Feb & Closed & \\
\hline
9 & Need of specifications & Meeting with the client & Thierry & 04 Feb & 04 Feb & Closed & \\
\hline
10 & Remember stuff to do & Actions table writing & Marion & 05 Feb & 04 Feb & Closed & \\
\hline
11 & Project management & Meeting with the industrial supervisor & Marion & 5 Feb & 5 Feb & Closed & \\
\hline
12 & Git Repository not well organized & Git cleaning & Thomas & 05 Feb & 05 Feb & Closed & \\
\hline
13 & Compatibility with the other team & Defining subskeletons format & Thierry & 06 Feb & 09 Feb & CLosed & \\
\hline
14 & Need of specifications & Meeting with the client & Thierry & 11 Feb & 11 Feb & Closed & \\
\hline
15 & The other group did'nt deliver binaries in time & Reschedule planning & Marion & 11 Feb & 11 Feb & Closed & 2 \\
\hline
16 & Binaries provided by he client are not compatible & Speak with the client & Thomas & 11 Feb & & Open & 4 \\
\hline
17 & Client new need & Contact the client by mail to know what we need to do & Thierry & 12 Feb & 12 Feb & Closed & 11 \\
\hline
18 & Project management & Meeting with the industrial supervisor & Amandine & 12 Feb & 12 Feb & Closed & \\
\hline
19 & Integration to do again & discuss with the client & Thierry & 25 Feb & 25 Feb & Closed &\\
\hline
20 & Project management & Meeting with the industrial supervisor & Emilie & 24 Feb & 24 Feb & Closed & \\
\hline
21 & Need of specifications & Meeting with the client & Thierry & 25 Feb & 25 Feb & Closed & \\
\hline
22 & The client need CMake to compile the code & Use CMake compilation & Thomas & 27 Feb & 27 Feb & Closed & \\
\hline
\end{tabular}
\caption{Actions table on February 12th}
\end{table}